First day of work on site
Today is the first day of physical work on the site. Ground&Water are carrying out drilling down to 15 metres deep to prepare the soil investigation report. This is essential for the calculations for the basement design. Drills! Ground&Water protecting our neighbours lawn: The equipment is on site! A sample collected from the drill: Deep hole: Collected soil samples for the analysis: We needed to use brutal force to get the drilling equipment to the old tennis court: The equipment is on the tennis court. This is the second and final hole