Only one section of the wall left Get link Facebook X Pinterest Email Other Apps February 26, 2021 The excavator is out - ready to complete the last section early next week Read more
Clearing the section for the last piece of slab Get link Facebook X Pinterest Email Other Apps February 16, 2021 Read more
Freezing conditions Get link Facebook X Pinterest Email Other Apps February 10, 2021 Freezing conditions delayed pouring the slab under the cinema and the rest of the walls. Read more
Electricity finally connected! Get link Facebook X Pinterest Email Other Apps February 09, 2021 Read more
New machinery arrived for backfilling Get link Facebook X Pinterest Email Other Apps February 09, 2021 Read more
Large delivery day Get link Facebook X Pinterest Email Other Apps February 05, 2021 Large delivery day on 5 Feb with steel beams, blocks for internal walls and mesh for the floor delivered. Read more
Wrestling the weather gods Get link Facebook X Pinterest Email Other Apps February 01, 2021 Water arrived over the weekend - 300mm deep Read more